Women’s Safe House – Update #25

July has seen continued excellent progress. At the beginning of the month, the large second floor slab was poured.

Plastering began. The interlock brick walls will remain exposed.

The third floor columns were started.

By the end of the month, plastering was progressing well . . . . .

. . . . . and the next level of walls was underway.