Women’s Safe House – Update #28

During October, the top floor walls progressed

It is now possible to get a real sense of the building in its setting:

By the first week in November, the top floor walls are finished. The next stage is the roof.

Women’s Safe House – Update #27

At the end of the first week of September, the third floor slab was poured.

In week 3, the last floor columns were placed

By early October, plastering and internal works are progressing well.

Smooth floors!

Women’s Safe House – Update #26

The building was already looking impressive at the beginning of August . . . . .

. . . . . and good progress has continued through the month, with the walls on the third level going up

The project is getting closer to the third floor slab

Formwork is completed, and the slab will be poured in the next few days

Women’s Safe House – Update #25

July has seen continued excellent progress. At the beginning of the month, the large second floor slab was poured.

Plastering began. The interlock brick walls will remain exposed.

The third floor columns were started.

By the end of the month, plastering was progressing well . . . . .

. . . . . and the next level of walls was underway.