Women’s Safe House – Update #18

In early March, the lower floor layout is really starting to take shape – with interlock brick walls and door and window frames made from locally harvested wood. These rooms will be mostly offices and an isolation wing.

Lintel beams are being cast, and work has started on the first stairs.

The excellent progress continues and there is a site visit from the local mayor and DCC chair and a government engineer.

What do you think of this update?

This site uses Akismet to reduce spam. Learn how your comment data is processed.