At the end of the first week of September, the third floor slab was poured.





In week 3, the last floor columns were placed

By early October, plastering and internal works are progressing well.






Smooth floors!

The building was already looking impressive at the beginning of August . . . . .

. . . . . and good progress has continued through the month, with the walls on the third level going up





The project is getting closer to the third floor slab








Formwork is completed, and the slab will be poured in the next few days




July has seen continued excellent progress. At the beginning of the month, the large second floor slab was poured.


Plastering began. The interlock brick walls will remain exposed.


The third floor columns were started.


By the end of the month, plastering was progressing well . . . . .


. . . . . and the next level of walls was underway.


Soon after the middle of June, the second floor is now virtually complete, and tied into the grade beams of the third floor.




Approaching the end of the month, you can see the third floor tie in of the grade beams behind the shear wall.


The next suspended floor slab will soon be ready for pouring

