By the middle of July, work is well under way with plastering the walls and ceiling of the previous ground floor.





June ends with the pouring of the concrete for the second floor roof slab!




By the third week of June, the bamboo and steel sheet formwork is ready for the new second floor roof slab.





The reinforcing for the slab is placed.




During the first week of June, the walls are complete.