By early February, the shear wall reinforcing is progressing, and the first delivery of the interlock bricks has arrived on site.
At the end of January, the substructure and foundations walls are complete. The overall footprint now clearly shows the size of the building!
Before the end of January, brick production is well advanced. Shipment to the site will start soon.
By the fourth week of January, the grade beams have been completed, along with below grade column bases. Work is now staring on the stone foundation walls.