Progress at Mahendra School – #4

It rained heavy and solid right through the night last night. As a result the completed excavation for the grade beams done yesterday collapsed, about 50%. When Carrie and I turned up to site this morning, we helped dig them out, heavy thick red clay. They are now just starting to stone shoring between the footings, then the grade beam forming and rebar, hopefully there will be a bit of a break in the rains soon.