Kharang Sharada school – construction update #3

During the first week of June, the walls are complete.

Kharang Sharada school – construction update #2

By the end of May, there’s good progress on the double wythe red brick infill walls with reinforced cast in place concrete lintel beams.

Kharang Sharada school – construction update #1

The first construction materials arrived on site at the end of April. By mid May, concrete columns had been added to the existing single storey building.

Work began on the brick infill walls

Mahendra School – children move into completed building!

On 17 May, the children moved into the new building – with an opening ceremony!