Women’s Safe House – Update #26

The building was already looking impressive at the beginning of August . . . . .

. . . . . and good progress has continued through the month, with the walls on the third level going up

The project is getting closer to the third floor slab

Formwork is completed, and the slab will be poured in the next few days

One Comment on “Women’s Safe House – Update #26

What do you think of this update?

This site uses Akismet to reduce spam. Learn how your comment data is processed.